Senior Planning Engineer, Worley Parsons Australia, Olympic Dam Expansion Project

START Date

Senior Planning Engineer - Worley Parsons

Upon joining WP I’ve been engaged with varieties of CAPEX projects within their Minerals and Metals group mainly including feasibility study and Definition as well as Execution phase project schedules for process plants and materials handling facilities. As senior planner I’m in charge organizing and steering all planning related activities for the project team to make sure the whole scope of projects has been covered and well time-planned in schedules.

Senior Engineer - Project Control, Praxair Asia Inc, Cryogenic Air Separation Plants

K
Kumar K 👤 Member for 19 years 5 months
START Date

Key Projects:

- PL4 Air Separation Project for United Steel, Bahrain

- T200 Air Separation Project for Bang-Pa-In, Ayuthaya, Thailand

 

  • Assistant Project Manager responsible for engineering and construction co-ordination.
  • Executed the project with engineering team in China and Construction management team from India.
  • Responsible for Schedule and Cost.
  • Prepared proposal cost estimates for the air separation plants for Middle East proposals.
  • Presented monthly

Lead Project Control Engineer, "Reliance Industries Limited, India", EPC of New Onshore Gas Plant upstream & Compression Facilities

START Date

Current Role

Working as Lead Engineer (Project Controls) and involved in Project Control activities of KGD6 – 80MMCMD Onshore Gas Terminal Project (Green field) at Kakinada (AP) commencing from Dredging works, Site Grading, Piling Works, Construction Jetty and Infrastructure facilities establishment till Commissioning of Onshore Terminal Project including Infrastructure Buildings 

Responsibilities:

  • Interface with Construction manager, Project Control Manager and Discipline leads
  • Preparation of WBS, Construction Schedules and Pro

Senior Planner/Programme Controls Manager, Parsons Brinckerhoff International, North West Gas Alliance (NWGA)

START Date

I am currently the Programme Controls Manager on the North West Gas Alliance (NWGA). I am in charge of a team of 4 planners where we plan and control the lay and abandonment of 526km (£100 million). We use Primavera P6 which is connected directly to the Commercial, Noticing and Validation databases to input or/and view data from our database.

Planning Engineer, Wade Adams, Tendering and controll

START Date
END Date

•            Preparing project execution program as specified in the Conditions of Contract (Clause 14).

•             Preparing Internal Programs for execution of works.

•             Monitoring progress and updating weekly progress.

•             Preparing projections of plant, material & labour.