Primavera Planning & Scheduling

Project Planner, TIME Plessey Telecommunications S/B, TIME Telekom Project

START Date
END Date
  • Develop a detailed schedule for the TIME Telekom Network Construction covering laying the duct, fibre optic cables along Peninsular Malaysia (3,600 km), laying submarine fibre optic cables (1,624 km), cabins installation and rooms
  • Monitor daily and weekly progress on all duct constructions, fiber optics laying including way leaves and permits
  • Produce and report the monthly progress status to General Manager
  • Provide analysis on the existing LAN and document all workstations and servers specifications
  • Propose and implement new Network Communication Infrast

Senior Planner, Sapura-Tomen-Harris (STH) Consortium, Kuala Lumpur International Airport (KLIA) Project

START Date
END Date
  • Develop plan, schedule and monitor progress for the entire systems network of KLIA including OPS, ISP cabling, cable termination, network hardware installation, functional test of LAN and commissioning of voice/data circuits
  • Co-ordinate closely with other Package Contractors to ensure work is completed on schedule
  • Produce weekly and monthly network progress reports to Client (KLIA Bhd)
  • Updates the schedule for all 14 sub-systems KLIA TAMS (Total Airport Management System)

Assistant Program Manager, ADtranz Transportation S/B , STAR LRT (Light Rail Transit) Phase II

START Date
END Date
  • Planning and scheduling for E&M works for Power Supply, Telecommunication, Automatic Fare Collection, SCADA and Rolling Stock for STAR LRT Phase II
  • Liaison with civil partner for the integration of E&M schedule
  • Produce three-weekly programme, E&M Works Programme, Target programme and Monthly Progress Report
  • Manage and develop the Project Progress Reports not limited to Monthly Progress Report, 3 Month Rolling Programme, Key Issues Report, Subcontractor Document Submission Schedule
  • Generate monthly progress payment claims for work completed

Track Enabling Works Planner, Balfour Beatty Major Civil Engineering & Metronet, London Underground PPP

START Date
END Date

 

01/2007 – 10/2008           Balfour Beatty Civil Engineering/Metronet         Track Enabling Works Planner

 

The job involved using the Track Renewal Programme for the London Underground to make changes to the Track Enabling Works schedule. Failure to deliver on time cost millions of pounds making our working environment fast paced and high pressured.

 

Key Responsibilities & Achievements:

Billing, ERA INFRA ENGINEERING Ltd, Thermal Power Plant

V
Vishal Jure 👤 Member for 14 years 9 months
START Date
END Date

PROJECR :       INDRA GANDHI SUPER THERMAL POWER PLANT (500 X 3 MW), Jharli (Jhajjar)

Responsibilities:

 

·         Coordinating with senior officials for various site activities and interacting with commercial, accounts, contract administration, estimation, drawing departments for various requirements in executing the projects.

Project Planner, ETA - ASCON, Dubai, UAE, 3B+GF+12F+LR+UR+Swimming Pool Hotel & Apartment Bldg at Al Raffa, Dubai owned by Al Ghurair Investment LLC

START Date
END Date

Planning Engineer/ Project Planner, assisted Project Manager in the monitoring and updating of site progress, resource utilization, and cash flow of Al Raffa Proj. Prepared monthly and weekly progress reports on site. Monitored and updated all the subcontractor’s construction programme, resource histogram, shop drawing submission and material procurement schedule. Coordinate between client, consultant and subcontractors on all site and progress related issues. Prepared monthly cost presentation for the company’s internal monitoring of cash flow.