vAROUND 8 YEARS OF EXPERIENCE INCLUDING 4 YEARS IN SAUDI ARAMCO (PETRO RABIGH, SAUDI ARAMCO DHAHRAN AND SATORP JUBAIL )
vEXCELLENT KNOWLEDGE IN PRIMAVERA 3 & 6.7, AUTOCAD, MICROSTATION
vANALYSIS OF ALLOCATING MANHOURS AND COST PER ACVTIVITIES
vPREPARE CHANGE ORDER
vMULTI DISCIPLINE CONSTRUCTION PROJECTS
vPROJECT MANAGEMENT AND TRAINING
vSUPERVISION IN ALL ASPECT OF DISCIPLINE
vMATERIAL TAKE -OFF
Educational Qualifications
- Tertiary – Saint Louis University
Degree
License Civil Engineer (099190)
Certification / Training Courses Attended:
Certificate
:
Autocad 2007, (computer aided design)
Certificate
:
Primavera 3, Project Management
Certificate
:
Staad Pro
Certificate
:
Civil Engineering Specialist
Analysis and Design Bridges
Brief Profile:
v Civil Engineer background with more than 8 years experience.
v Vast experience in executing the tasks pertaining to the projects.
v Vast experience in Primavera , AutoCAD and Microstation
v Vast experience in Material take-off
v Vast experience in Costing
v Prepare Billing Monthly Performance Valuation
v Prepare Baseline Schedule from start to finish including Milestone
v Prepare Schedule Activities from Start to Finish including Milestone.
v Prepare Schedule of Major material (equipment) upon Installation.
v Prepare Schedule of Installation of Equipment Before Shutdown.
v Prepare Mobilization of Manpower upon date of requirement.
v Prepare Mobilization of Equipment (ex. Backhoe, etc...) upon date of requirement.
v Prepare Monthly/Weekly Meeting Report for Client ARAMCO
v Prepare 6months, 3months, and 2weeks Look ahead schedule
v Prepare Reports for the Company (s-curve, histogram)
v Prepare Monthly Progress Billing Reports
v Prepare Schedule impact per Change Order
v Prepare Change Order
v Coordination weekly meeting with client (ARAMCO)
v Coordination meeting with the Procurement to ensure the priority material must be on-time delivery.
v Monitor Daily Accomplishment Activities
v Organize and Conduct internal meeting (company) to ensure baseline schedule implemented.
v Identify and record all actual activities for future reference.
v Finely handing over the projects to the satisfactions of the clients.
Summary of Work Experience (From present to previous)
Name of Company / Country
:
M.S.AL-SUWAIDI INDUSTRIAL SERVICES CO. LTD. P.O. Box No.991 Al-Jubail, 31951, K.S.A.
Position Held
:
PLANNING ENGINEER
Period
:
AUGUST 2007 - JUNE 2011
Key Job Responsibilities
:
· Prepare Construction Baseline Activities schedule from Start to finish including Milestone.
· Prepare Material Baseline Schedule from start to finish upon Installation.
· Prepare Shutdown Schedule.
· Prepare Mobilization\Demobilization Manpower
· Prepare Mobilization\Demobilization of Equipment.
· Prepare 6months\3months\2weeks look ahead.
· Prepare Activities for All Discipline.
· Prepare Monthly Performance Evaluation
· Prepare Cost Impact Analysis
· Prepare Change Order
· Coordination meeting weekly with the Project Management Team (PMT)
· Coordination meeting with the Procurement.
· Coordination meeting with the Technical Team.
· Responsible for Internal meeting (company) for the strategic plan of the project.
· Monitoring Daily Accomplishment
· Submit Monthly, Weekly Report including S-curve and Histogram
· Identify and Record Actual Activities for future Reference.
· Finely handling over the Projects to the satisfaction of the client.
Name of Company / Country
:
MASAITO DEVELOPMENT CORPORATION/ PHIL.
Project
:
REAL STATE
Position Held
:
PLANNING ENGINEER
Period (From – To)
:
JULY-2006 - AUG-2007
Key Job Responsibilities
:
· Prepare Construction Baseline Activities schedule from Start to finish including Milestone for the sub-contractor.
· Prepare Bill of Quantity.
· Prepare Bill of Material.
· Prepare Progress Billing
· Prepare Change Order
· Prepare Job Order for all Sub-Contractors.
· Prepare all Drawings including Shop Drawings.
· Prepare Weekly Report for the Top Management
· Prepare Monthly Financial Report.
· Organize weekly Meeting for the Sub-Contractor.
· Attend Testing of Compressive Strength.
· Evaluate Billing for Sub-Contractor.
· Establish Quality Procedure and Monitor the implementation including work instruction.
· Identify and Record all Actual Activities for future Reference.
· Finely handling over the Projects to the satisfaction of the client.
Name of Company / Country
:
SUPERCITY REALTY DEVELOPMENT CORPORATION (EXTRA ORDINARY) PHIL.
Position Held
:
PROJECT ENGINEER
Project
:
REAL STATE
Period (From – To)
:
SEPT 2005 - JUN-2006
Key Job Responsibilities
:
· Prepare Construction Baseline Activities schedule from Start to finish including Milestone for the sub-contractor.
· Prepare Bill of Quantity.
· Prepare Bill of Material.
· Prepare Job Order for all Sub-Contractors.
· Prepare all Drawings including Shop Drawings.
· Prepare Weekly Report for the Top Management
· Prepare Monthly Financial Report.
· Organize weekly Meeting for the Sub-Contractor.
· Conduct Field Density Test.
· Conduct Slump Test.
· Conduct Boring Test.
· Checking Coordinates/Elevation.
· Attend Testing of Compressive Strength.
· Evaluate Billing for Sub-Contractor.
· Establish Quality Procedure and Monitor the implementation including work instruction.
· Identify and Record all Actual Activities for future Reference.
· Finely handling over the Projects to the satisfaction of the client.
.
Name of Company / Country
:
A.E. ASPIRAS ENTERPRISES
Project
:
HOUSING
Position Held
:
PROJECT SITE ENGINEER
Period
:
APRIL 2003 - AUG-2005
Key Job Responsibilities
:
· Prepare Estimate
· Prepare Bill of Quantity
· Prepare Bill of Material.
· Prepare Drawing including shop Drawing.
· Prepare As-built
· Direct Supervision of Manpower.