)Planning

Senior Planning Engineer, ETA ASCON, High rise Buildings

START Date
END Date
Experience Hours (Planning & Scheduling)
10000
Experience Hours (Cost Management)
7550
Experience Hours (Forensic Analysis)
3050

Current Role

Project Planning & Management

§  Preparation & Monitoring of Construction Master Programme.

§  Scheduling project including material & manpower planning.

§  Anchoring on-site construction activities to ensure completion of project within the time & cost parameters and effective resource utilization to maximize the output.

EPC Senior Planner, Emirates Technical Associates, 220/132/33/22/11kV Substations

START Date
  • Prepare / Review and approve / comment / finalize on the Engineering (Design), consultant/vendor, Budget, Procurement, Construction  & Commissioning schedules as submitted and ensure the Schedule is in compliance with the overall project schedule through critical path method and advise the concerned of any deficiencies from standards.
  • Continuously monitor, against approved schedules, the Contractor’s major construction progress and ensure equipment and manpower are adequate or in case of any shortage report to concerned.

PLANNING ENGINEER, Gammon & Billimoria LLC, 31nos. G+4 Residential buildings

START Date
END Date

Project: International city Package 07

Client – Nakhel, Dubai

31 residential Apartments for International city developed by Nakheel at Dubai, U.A.E.

Project Value : AED 400 Millions

Achievements: Prepared micro planning for all the activities and closely monitored the same, flagged up the issues and risks involved so that achieved the first 2 miles stones of the project.

Introduced new and user friendly practice for easy and close monitoring of activities.





Responsibilities:

Assistant Project Planner, BK ASIA PACIFIC, 1)Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date

 

 

BK Asia Pacific provides a comprehensive network of Project Management, Commercial and Contract Management, Specialist Procurement and Contracting Services to the local and international construction industries.

Planner / Project Manager, McCabe builders uk ltd, Eagle house

START Date
END Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
1000

Current Role. On a day to day basis I am responsible for the management of the McCabe Eagle House site team together with ensuring correct control of both safety and construction activities of the Eagle House Project are maintained.

My role also includes management of the design team to ensure clients requirements are integrated into the design and ensuring programme , finish and cost controls are adhered to.

i undertake all planning and programming of the project and oversee any consultant design team meetings and subcontractor meetings that are taking place.

Senior Planner, JMZ Engineering & General Construction , Villas & Townhouses

START Date
END Date

•Provide technical advice regarding construction, and structural repairs.
•Provide technical advice on cost control, planning, PERT-CPM scheduling, and safety measures and procedures;
•Guides team from interpretation of plans to materials take-off and costing, procurement, manpower scheduling and project construction

Project Planner, ACC, Princess Tower, 107 Floor Tower

START Date

Working as a Project Planner for PrincessTower(107 storey). World’s Tallest Residential Tower at Dubai Marina. 

Job Function      :           Making Base Line Programme (18000 activities).updating the Program, Review Sub Contractor’s Programme, Resource Loading (Man-hours, Quantity & Cost). Cash flow, Histogram, Weekly & Monthly Reports.