Trainee Planner / Technical Assistant, Doosan Babcock, Plant shutdown maintenance

START Date
END Date

I spent from September 2008 to December 2009 as a Trainee Planning Engineer for Doosan Babcock. 

During my employment which ended due redundancy I took on several projects. 

While working in Cockenzie Powerstation (East Lothian) I ran and maintained a full unit shutdown as well as getting contracted to refurbish pipework in a distillery in Edinburgh.  As well as these I ran basic maintained work on the station.

Project Management Consultant, Eni (Agip), Various Projects (Head Office Position)

START Date
END Date

Project management advisory capacity to 5 project managers on various offshore and onshore engineering projects. 



Introduced a working form of Prince 2 management methodology to the Projects department by gradual implementation of processes. 



Demonstrated a quantum improvement in project visibility and control on a programme of 10 projects with combined value of over $240 million (USD). Used and trained others in MS Project, Filemaker Database and Mindmanager tools. 

Senior Planner System Wide, Sasol, Upstream gas Processing Plant (EPC)

START Date
END Date

 

2009 Jan – 2010 Jan and 2008 Jan – May: Sasol Petroleum International, South Africa

Based in Johannesburg on a consultancy basis to assist in the establishment of high level planning and project controls using the Primavera P6 tool. Specifically, the contract was to realise systematic control of SPI up-stream gas exploration and development project activities in Mozambique and elsewhere, including:

Senior Planner Engineering, ARCAN Project Management Services, high raised & complex projects based in Dubai ,UAE.

M
Mai Tawfeq 👤 Member for 16 years 3 months
START Date

- Develop and check detailed schedule for Design, Engineering, Procurement, and Construction Phases.

- Interrogate inter-discipline schedule requirements and restraints to ensure logical work sequences across all disciplines of the project.

- Update and check of Time schedule indicating Target Planned vs.

Senior Project & Planning Engineer, OGASCO (Oil and Gas Construction Co.), FABRICATION OF EQUIPMENT AND STRUCTURES FOR OIL FACILITIES

START Date

Responsible for project management, planning and Monitoring the project in Engineering, Procurement & Fabrication phases such as:

 Fabrication of SBM & CBM CALM Buoys – Client: SBM Offshore Services Inc.

Fabrication of Pressure Vessel, Heat Exchanger, Silo, Column, Tank –Client: Gulf Fluor

Construction Planner , P Elliotts, Athletes Village

START Date

1. Detailed Construction Programmes.
2. Resource Histogram’s.
3. Plant Histograms.
4. Construction Sequence Drawings.
5. Construction Methodology.
6. Project Logistics Plan and Site Set Up Plan.
7. Project Crane Co-Ordination Plan.
8. Traffic Management Plan.
9. Respond to Technical Questions during the Bid Stage
10. Quality Assurance and Bid Plans and Company Policies
11. Health & Safety Plan in Conjunction with Health & Safety Department.
12.

Senior Planning Engineer, C&D Industries Ltd, Aircraft Alliance for new Queen Elisabeth Class.

R
Ron Baird 👤 Member for 19 years 3 months
START Date

Senior Planner.

Plan using Microsoft 2007 and P3 the Design, Manufacture, Installation and Commissioning of HVAC for 2 Aircraft Carriers.

Liaise with 5 Dockyards concerning the Installation of HVAC

Integrate 24 various plans of differing Modules being built in 5 Shipyards for completion in Rosyth Dockyard.

Produce fully costed and resourced level 4 plans.

Report progress via scorecards iaw approved procedures.

Detail Project Management Plan and Responsibility Matrix for internal use.