planning

production of project plans

Graduate Project Manager, Highways England, Road Investment Porgramme

START Date
END Date
Experience Hours (Planning & Scheduling)
0
Experience Hours (Cost Management)
0
Experience Hours (Forensic Analysis)
0

Providing support in the successful delivery of multiple projects.

Planning and defining project steps, scope, project risks and issues, establishing plans, reviewing milestones.

Identifying resource requirements and interdependencies.

Updating and providing end of month reports to the project board.

Field Planner, Civmec Construction & Engineering Pty Ltd., Ichthys’s Onshore LNG with Civmec Construction

START Date
END Date
Experience Hours (Planning & Scheduling)
300
Experience Hours (Cost Management)
300
Experience Hours (Forensic Analysis)
50

Field Planner - (CCPP) - Ichthys’s Onshore LNG with Civmec Construction

Aug. 2017 to June 2018 – Civmec Construction Australia

Civmec Construction – Darwin Offshore Logistics Base - Darwin

 

Advisor Planning - Sr Planning Engineer, Projeqz, Down Town Jabel Ali

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
2000

 

Project                        :           DownTown Jebel Ali - 2 Blocks Office and 2 Blocks of

Senior Project Scheduler, ThyssenKrupp, HHCR Rütgers

START Date
Experience Hours (Planning & Scheduling)
600

Senior Project Scheduler for thyssenkrup Industrial Solution, Dortmund, Germany

project production plant of hydrogenated hydrocarbon resins (HHCR) in Castrop-Rauxel, Germany

Setup and maintenance of the Procurement and Construction Schedule

https://adhesives.specialchem.com/news/industry-news/rain-carbon-design…

Lead Project Scheduler, epcm projektmanagement GmbH, 2017 Turnaround

START Date
END Date
Experience Hours (Planning & Scheduling)
900

Lead Project Scheduler / Lead PMO for Projects and Turnarounds

epcm projektmanagement GmbH, Haltern am See, Germany

 

Development of tools for Schedule Assesment

Planning, Scheduling, Progress Reporting of a Turnaround for Bayer, Dormagen, Germany

Timely completion of the Project on the 18th of August 2017.

 

Lead Project Scheduler, SMS Siemag, CC6 Continuous Caster

START Date
END Date
Experience Hours (Planning & Scheduling)
3500

Lead Construction Scheduler on behalf of SMS SIEMAG AG

20 months Site operation, planning and scheduling assembly and commisioning jobs

Project: Continuous Caster CC6 for the Dillinger Hütte AG, Dillingen an der Saar, Germany

timely completion 3 September 2015

Asst. Manager Implementation, U-Foam Private Ltd, Telecom Projects

J
Joe Raj 👤 Member for 20 years
START Date
END Date
Experience Hours (Planning & Scheduling)
7000
Experience Hours (Cost Management)
1400

Asst. Manager - Implementation

U-Foam Private Ltd (Major Telecom Projects)

-          Planning, Co-ordination & Implementation

-          Pre-fab buildings & associated civil works

-          Operations spanning 16 states in India

-          Cash-flow forecasts, Resource deployment