Delay Analysis

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Senior Planner, Larsen & Toubro (L & T) Limited, Offshore Platforms and pipelines

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
4000

• Project planning, scheduling, monitoring, updating, controlling & co-ordination of the offshore oil & gas project.

Managing & Senior Consultant, Hill International (Claims), Various

L
Lee Mallek 👤 Member for 21 years 1 month
START Date
END Date
Experience Hours (Forensic Analysis)
7100

Relocated from Bermuda to the Middle East to specialise in delay analysis initially in the contracts and claims team based at Muscat International Airport. Projects included the following:

Power Plant – Boiler Unit, Kudgi, India

Worked as the delay analyst performing time impact analysis over 21 No. time slices for one of three boiler unit’s extension of time claim. Responsibilities included supervision of a consultant, delay analysis and producing the final report.

Director, Laurent Giles Technical Services Limited, Various large luxury yacht construction and refit projects

START Date
END Date

Project management of several large luxury yacht construction and refit projects. Independent expert witness in yacht construction disputes and forensic delay analysis in High Court, arbitration and adjudication proceedings.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.