Delay Analysis

Freelancer Planner, and Quantity Surveyor Consultant, Consultant, More than 15 Projects

START Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
2500

La Constructa (Contactor’s Planning Consultant):

- Keen3,4,5,6-Beit Misk, Erga, 4 Buildings 6Stories, $8 Million, PS: 28May14- PF: 24Mar14

- USEK-BMB, Byblos, 3 Blocks 8 Stories, $11 Million, PS: 1Jun13- PF: 31Jan16

- LAU Parking, Byblos, LAU, Eng.: DG Jones, 6 Stories, $5 Million, PS: 14Feb13- PF: 4Feb14-AF:14Mar14

Controlling and Operations Manager (As a consultant), PMM s.a.r.l, Multiple Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
1000

Multiple projects, 30 buildings, from 10 to 45 stories, $40 Million total budget.

• Leading the Planning and Quantity Surveying teams.

• Make clients’ site and office visits, and attend progress meetings.

• Create new and revised baseline schedules; follow up the control and updating procedures, and claims.

• Implement new procedures for the department and the company

Delay Analysts and Senior Planning Consultants, ACC- Matta, Lebanon Water Front City

START Date
Experience Hours (Planning & Scheduling)
200
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
200

10 Luxuries Buildings 12 Stories each and a promenade $250 Million Budget.

* Prepare basline schedule.

* Submitt biweekly updates, and reports.

* Prepare delay analysis, and extension of time claims.

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
2500
Experience Hours (Forensic Analysis)
2500

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove