Delay Analysis

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

Planning Manager, Depa Abu Dhabi, Cleveland Clinic Abu Dhabi

START Date

Planning Manager at Depa Abu Dhabi, Cleveland Clinic project.  Packages include Partitions and Specialist Ceilings, and also Specialist Joinery.

Roles na dresponsibilities include overseeing of planning on Cleveland Clinic, from Tender stage through to completion and handover. Weekly progress reporting and updating of planning, identification of constraints, risks to project completion. Analysis of delays and compilation of claim documantation.

CONSULTANT PLANNER, Dale Hill Associates, (various projects)

START Date

Professional project management consultant, working in all sectors of the UK construction market. Providing services to one-off clients, developers, contractors & sub-contractors. Dale Hill Associates provide Quantity Surveying and programme management skills to supply or supplement in-house resources on both long-term contracts and on an ad-hoc basis.

Design Coordinator & Planning Engineer, Murray and Roberts Middle East, Al Raha Beach, Lu'Luat Island, Private Beach and Jellyfish Island

START Date
END Date

Four concurrent design & construct sea wall installation projects in Abu Dhabi at Al Raha Beach, Abu Dhabi, UAE

Project Planning Engineer, Murray and Roberts Australia, Australia, Barrow Island, GORGON LNG Project, Pioneer Material Offloading Facility

START Date
END Date

Project Planning Engineer

June 2010 – October 2012 PMOF, Gorgon LNG Project, Barrow Island

Lead Planning Resource for design, procurement & construction of marine/ offshore materials offloading facility. AUD 500 million

Corporate Project Controls Manager, Jacobs, All Onshore and Offshore Projects

START Date
Experience Hours (Planning & Scheduling)
36000
Experience Hours (Cost Management)
25000
Experience Hours (Forensic Analysis)
28000

Jacobs Zate (EPCM / EPC)
Saudi Arabia, Al Khobar
Projects: All Saudi Aramco GES+ Projects for both the Upstream and Downstream buniness lines:
Role: Project Controls Manager for the GES+ Aramco Contract (Upstream & Downstream)
Job Description:
Responsible for ensuring the project controls department delivers a cost and schedule effective, high standard of project controls services to all internal and external clients. Specific responsibilities include:
• To attract, assemble and manage a high-quality project controls team.

Assistant / Planning Engineer, Synergy Property Development Service, MultiSpecialty Hospital for DM Healthcare Group

START Date

With Synergy Property Development Services Pvt. Ltd., CochinProject: Proposed Hospital for DM Healthcare Group, “Aster Medcity”, at Cochin, Kerala, IndiaContract Amount: Rs. 3.5 BillionDescription: DM Healthcare Pvt. Ltd. is a healthcare service provider company with leading presence in Middle East and India, owning and operating a network of hospitals, polyclinics and pharmacies. DM healthcare is building a state-of the- art Medcity project in Kochi, Kerala, of contemporary international standards.