Australia (OC.AU)

AU

Alliance Planner & Scheduler, Alstom Power, Hydro-Power & Water Resources

START Date
END Date

Planning and scheduling of Poatina Power Station Modernisation & Refurb works.  Planning and scheduling for upcoming Tungatinah Modernisation Project and any other projects for the Alstom Power Division in Tasmania

Southern Region Planner - Tasmania, John Holland Group, All

START Date

Planner for John Holland Group, Southern Region, specifically Tasmania.  Initially seconded to Communications Group to complete the NBN Project in Tasmania.  Now providing assistance on UTAS MS2 Early Works and will be working on all other Tassie based projects.

Kevin Ranclaud

First Name
Kevin
Last Name
Ranclaud
Professional Since
Oldest experience
Years Experience
5
Telephone Number
+61-(0)421-456-802

Aug-2012 to Feb-2013 - Kellogg Brown and Root Project Scheduler for Rolls Royce Australia Services/ KBR AASIMS Project contract with Defence Materiel Organisation, Sydney Australia.

Project Cost Controller, Thales Australia, JP2070 Project Djimindi Alliance Lightweight Torpedo Project

START Date
END Date

• Maintenance of the project Performance Measurement Baseline.
• Maintenance of the Cost/ Schedule Control System documentation, including Earned Value Management and Scheduling.
• Develop and maintain the Earned Value System Description and Earned Value Management Plan in conjunction with the Project Scheduler.
• Collect monthly Earned Value progress from Control Account Managers and Alliance partners.
• Preparation of monthly Cost Schedule Status Reports using Cobra Cost Processor.
• Analysis of project performance using Earned Value methodologies.
• Participation in Integrated Baselin

Project Controller, KBR Kellogg Brown and Root Pty Ltd, AIR9000 Training Development Project

START Date
END Date
  • Maintain the Earned Value Management System consisting of project master schedule, implemented in Primavera, and cost reporting, using Cobra software.
  • Maintain the Contract Work Breakdown Structure (CWBS).
  • Maintain the CWBS Data Dictionary.
  • Maintain the project Performance Measurement Baseline.
  • Issue and control all baseline change request documents.
  • Produce Master Schedules incorporating WBS and task elements.
  • Participation in integrated baseline reviews with project prime.
  • Review and update the project Earned Val

Project Controller, KBR Kellogg Brown and Root Pty Ltd, AIR5402 MRTT Air to Air Refuelling Project

START Date
END Date
  • Maintain the AIR5402 project schedule, implemented in Open Plan Professional (OPP) software.
  • Maintain the AIR5402 Project Work Breakdown Structure (PWBS).
  • Maintain the Contract Work Breakdown Structure (CWBS).
  • Maintain the project Performance Measurement Baseline (PMB).
  • Guidance and support in the use of scheduling and reporting tools to Project Office Staff.
  • Develop and prepare project performance reports to the Improve Project Scheduling and Status Reporting (IPSSR) Program standard.
  • Analyse the Contractor’s sch