The Spear Group Lead Planner
Master Scheduler representing Client
Master Scheduler representing Client
2000
Centocor
Project Planner
Contracted to advice several task force teams about general set-up, structures and future development of a start-up planning for their new build “Remicade” pharmaceutical plant.
Duties: to inform management about planning possibilities
to advice about all aspects of building a planning
to advice about and start an info and data flow.
The tools: MS project.
Location: Leiden, Nl.
Procurement by Isoper BV, Rotterdam.
Current Role
Planning and progress reporting on site based projects and maintenance planning.
Including break down of hours from target costs and estimates for integration into the overall programme, site measures, collation of progress information from external contractors, reports, S-Curves and programme updates to reflect progress.
Bill O’Brien has over 20 years’ experience in scheduling, planning, delay analysis and risk management across a wide array of industries, including Life Sciences, High Rise Commercial, Mission Critical Data Centers, Industrial Process Plants, Rail, Power, Pharmaceuticals, Healthcare, and M&E. He has worked internationally on complex EPC projects, putting his in-depth knowledge of CPM scheduling, risk management, delay analysis, and more to work around the globe.
• Master scheduler and project controls support for 3 manufacturers and 8 pharmaceutical campuses.
• Build and maintain high level schedules for corporate funding and capital delivery processes.
• Provide analysis and conduct review sessions for third party construction and system integration schedules.
• Create detailed cost & resource loaded schedules to track execution of commissioning & validation protocols for new pharmaceutical manufacturing facilities.
Current Role