Civil Planning Engineer, Shimizu Corporation, Petro Chemical

START Date
END Date

 

- Update Master Construction Schedule with actual progress data as project progresses.

- Prepare short-term schedules (2-weeks or 2-months look ahead schedule) based on the approved Master Construction Schedule and actual resource available ( manpower, material, equipments, drawings);

- Update progress report and daily work accomplishment;

- Update physical work accomplishment and work schedule;

Mohd Anjum

M
Mohd Anjum 👤 Member for 15 years 5 months
First Name
Mohd
Last Name
Anjum
Oldest experience
Years Experience
41
Telephone Number
+966895974036

Project planning, Progress Monitoring and tracking, Primavera 6.7, MA Access, Ms Project

Planning Engineer, GAS Arabian Services Co Ltd., Sales Gas PipeLine Project to PP-II, Wasit Utilities System,Core Hydrocarbon Facilities(Pipeline project)

M
Mohd Anjum 👤 Member for 15 years 5 months
START Date
END Date

Curremtly Working as a Planning Engineer in one of the EPC company

and doing one of the project of "Sales Gas Pipeline Project for PP-11"

As a Planner i got total 2 years of experience in Oil and Gas Sector with hands on experience in project planning and scheduling Utilities ,Pipeline and other construction Project using tools like Primavera P3 and P6 and 7(P6.7).

familiar with MS Project with fluency in MS Excel and MS Access DB.

Controls and Budgeting Senior Engineer, Project planning, China National Petroleum Corporation (CNPC) International Limited, Development of the heavy and light oil reservation in the North Azadegan field

START Date
END Date

 

Project Description:

EPCC Contract for the development of the heavy and light oil reservation in the North Azadegan field, Iran. Establish a production level of 150000 bbl/d, drilling new wells and construction of surface facilities.

Client: National Iranian Oil Company (NIOC), surface facilities Basic Designer: Mott McDonald (Canada) and China Petroleum Engineering Co. (CPE)

Responsibilities:

Mark Moggridge

First Name
Mark
Last Name
Moggridge
Oldest experience
Years Experience
41

 

My latest employment was Site Planner for Woodside NR2 North West shelf expansion project in Indonesia. The project consisted of; Jacket (24,000 ton), two bridges and 16,000 tons of pile.

In additional to my standard Site Planning activities I developed the Jacket commissioning schedule which involved the creation of S-curves and Histograms for all stake holders. Once commissioning began, I was responsible for progressing and reporting of this schedule.

Planner, Woodside Energy Ltd, Woodside NR2 Project Substructure

START Date
END Date

 

 

 

 

I am experienced in planning, scheduling, Costing and Risk Management. My duties have included, monitoring project progress complying with approved project procedure and schedule. Performing schedule analysis, reviewing and risk assessment in order to meet project target completion dates.

I’m an advanced user of the Primavera P6 project management software with exposure to Microsoft project over my career.