Primavera Risk Analysis - Getting the absolute minimum and maximum
Hi all,
I have a very detailed risk analysis for my project (different risks, different uncertainties with different distributions,...). And now I would like to see the "absolute" minimum and maximum end dates.
Ofcourse since Monte Carlo Analysis is based on random iterations, I can never say with certainty what the shortest project duration is (think extremely happy flow, all uncertainties getting the minimum durations). I get the minimum from OPRA but next time I run the simulation I might get a new minimum (or maximum).