hi all
i have a question that bothers me
i work in a consultant firm and i review contractor's time schedules
the contractor submit a baseline in the begining of work and i get from it the cash flow
i compare this cash flow with invoices of the contractor during project execution
after 6 months the contractor had the approval of time extension for his work from the owner (1 year extension..!!)
the contractor made a new baseline showing the new project end date starting from the date the extension of time is approved till the new end date