At completeion cost not calculated automatically

Hi,

For cost monitoring we decided to record actual cost especially against material. On a demo project I loaded some material on various activities and to record actual cost I unchecked both “Auto compute Actual” and  “Calculate costs from units” because if I kept them check then though system allow me to enter actual cost but on using “Recalculate Assignment Costs” it recalculate by multiplying unit rate with actual units and in my case actual unit rates sometimes under or over at time of procurement. So in order to achieve Actual Cost without changing resource unit rate, I unchecked both options on resources.

When I add any new resource with same settings as above, it automatically computes “At completion Cost” if activity not started but if activity has been started it won’t.

And in my senario sometime we have to add resources even activity has been started.

Pls Advise.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts