getting rid of title block to increase plot space
is there anyway to eliminate title block to increase the plot area ?
mike
Questions & answers for Primavera software
is there anyway to eliminate title block to increase the plot area ?
mike
i currently have an item on a schedule called "shutdown"
i have introduced another item called "give 7 day notice prior to shutdown" and made its succesor "shutdown" and its pred "notice to proceed"
i want the date for this new item to always be 7 days before the shutdown item no matter how the schedule changes, so we can see it come up on the schedule and take action
i have tried several different ways to do this (too many to list) but the date of the "give 7 day notice" new item is never right ?
any suggestions ?
Hie, can anyone help me on this ?
I am not a planner but i know abit about P3.
I found a program file in my planner computer. However, there no prx. file here.
There is only 24 sub-files of the program.
How can i open this program or how to create a prx file out of this ?
Thank you.
Does P3 support project version history tracking? For example I would like to view an audit trail of project changes and potentially roll back changes if needed.
Thank you,
i am trying to print a gantt chart to a pdf file
i am doing a file, print setup, changing driver to pdf, selecting 11x17 format
for some reason it is just printing the item descriptions and column info but not any of the time scale info to the right of the columns
does anyone know how to have the timescale also included in the pdf print file ?
mike
Hi Guys, would appreciate any response on this one.
I'm just a newbie in using P3. I tried to insert columns other than listed in the column data. It says "blank column" on the data but I wanted to use: "total quantity", "UOM", and ""production rate".
Somehow I have managed to have the columns with the said title but I am not able to input any data in its cells. It seems that the cells are being locked or some sort of being disabled to revieve data. I wish to have these data in my layout for determining the required man-days for each activity but how will I proceed?
does anyone know how to cave a p3 project as a prx file ?
does anyone know how to cave a p3 project as a prx file ?
i have created a p3 schedule with 250 activities
the schedule is currently set to duration in days
the problem is there are 3 times during the project where a shutdown must occur and you have a 6 hour max window to complete all tasks
so our activities look like this:
shutdown
weld beam
install new valve
change pc controller
restart plant
since these items must be done in succession i want to do: shutdown (o days) - weld beam (2 hours) - install new valve (2 hours) -