Maintenance Scheduling
a
- Read more about Maintenance Scheduling
- 1 comment
- Log in or register to post comments
General planning comments and questions.
a
Hi Everyone,
For us www.planningplanet.com very good to discuss each and every topics as well as doubt also. Same like this forum,kindly request me other forum. It may helpful to everyone guys.
Thanks,
Vasanth
some random thoughts on how to build an integrated Project controls system using PowerBI
https://datamonkeysite.com/2017/04/18/integrated-project-control-system…;
HTH
Mimoune
Hello planners,
I am facing a problem in the project baseline. I received a baseline of 5,000 activities, where the resources are loaded wrong. The old planner placed the default units/time quantities in the column of budgeted labor units my mistake. Can someone guide me or help me in shifting them from the column of budgeted labor units to default units/time?
I tried to copy the program, and maintain it then assigning it. But when i go to the global changes, there is no column named as BL1 budgeted labor units.
Help me please.
Dear All,
I am currently conducting master thesis survey for my study of Time Delay Analysis Techniques Applied to Building Construction Projects in United Arab Emirates. I am seeking a support from Planners, Schedulers, Forensic Delay Analysts or Contract Administrators in UAE to answer the related survey questionnaires. I am requesting to anyone to leave your email address here so I can send it to you formally.
Looking forward for your kind support.
hi guys,
i want to make a labor histogram for interior fitout manufacture or production,
how can i make days ,hours for 4 month, i have labors catergory carpenter, fabricators, helpers.
with MS EXCEL i want to make siomple with 2d graph.please help me guys all i wnat is column and formula,hope i ll get some help
Dear Construction planner,
Is there soemone there who can confirm the work sequence for activities mentioned in the subject:
AFTER A/G piping installed, the sequence is as follow:
First painting (except the welds)
Second , install heat tracing (if aplicacble).
Third, hydrotest
Fourth, reinstament + final painting.
Final , Insulation.
Is this correct ??? any skilled construction planner out there.
Thanks in advance,
Carmen
Hi everyone,
Can anyone advise me how to manage and progress some job with no relationship to each other, for example: We have 100 junction box need to check during Turnaround, and each JB need only 1 hour to check. Please advise me? THanks
Hi,
Recently I have just amended my resources cost. I want to update my cost baseline by updating the current project by importing previous updated *.xer files. However, when I try to schedule my program it become 0% (except for the 100% activities). Can anyone advise me why does this happen? Or do I have to manually insert in the performance percentage manually one by one to each of the activities. Which by the way consist of more than 500 activities!!!
Thanks in advance guys
Dear all,
I was requested by my boss to come out with Pedestrian Brigre Work Program which i never produced before.
I will be glad if any expert in here willing to give opnion & sharing template for the peogram.
Send the template to my mail:- [email protected]
Regards,
Junior Planner.