Baseline submission to Client
Hi all,
I have a question.
In the Contractor's submitted baseline schedule to a Client, the Client planning enginner found that the design review by the Client (Engineer) is in the critical path of the project. How should he respond to it?
For eg: the sequence as; Design documents submittal (Contractor)-Design review(Client)- Design approval-Shop drawings /method statement preparation-major civil foundation construction-major equipment/mep works-commissioning-Completion