Dear Experts ,

When I checked our contractor's weekly and Monthly report , I found that each weekly and monthly period showing diffrent actual figures for the same month . I guess promavera just distribute the actuals over the period every time when it gets updated

My first question is - is this an reasonable reson to say that  data comes from P6 software ? or we have to do it manually to make sence ?

Second- Contrator is reluctant to use the option "Store period performance"  

your view please ?

Janaka

 

R
Raymund de Laza 👤 Member for 16 years 6 months

Actual Cost That was Auto Calculated by Primavera is a fancy Actual Cost. Actual Expenses is the Actual Cost supposed to be manually entered and it is supposed to be Saved periodically using the "Store Period performance".

 

Regards,

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Using store period performance will put the actual cost into the correct time frames.

why is the contractor reluctant to do this ?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Using store period performance will put the actual cost into the correct time frames.

why is the contractor reluctant to do this ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts