Resource Dependant
Hi all,
When setting up 'resource dependant' activity with a duration of 5 days, then assigning 5 resources to the activity with a shared resource calendar of 4h/d (0800-1200).
Can one still get the activities start, finish & duration to not change as the below is doing?

- Read more about Resource Dependant