Expenses Actual Cost Based on Activity Physical%

Hi,

 

I have added an expense to my activity.  Is it possible that the 'actual cost' of the expense change as physical % complete of the activity changes?

 

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

a Global chnage will not work here

export the physcial % complete and the Expense % complete to excel

thne copy the physcial % complete to the expense complete and then import back into p6

Z
Zoltan Palffy 👤 Member for 16 years 10 months

a Global chnage will not work here

export the physcial % complete and the Expense % complete to excel

thne copy the physcial % complete to the expense complete and then import back into p6