Hi,
I have added an expense to my activity. Is it possible that the 'actual cost' of the expense change as physical % complete of the activity changes?
Thanks
Hi,
I have added an expense to my activity. Is it possible that the 'actual cost' of the expense change as physical % complete of the activity changes?
Thanks
glad I could help
Thanks a lot Zoltan
Thanks a lot Zoltan
a Global chnage will not work here
export the physcial % complete and the Expense % complete to excel
thne copy the physcial % complete to the expense complete and then import back into p6
a Global chnage will not work here
export the physcial % complete and the Expense % complete to excel
thne copy the physcial % complete to the expense complete and then import back into p6