Resource Dependant

Hi all,

When setting up  'resource dependant' activity with a duration of 5 days, then assigning 5 resources to the activity with a shared resource calendar of 4h/d (0800-1200).

Can one still get the activities start, finish & duration to not change as the below is doing?

xxxx.jpg

Z
Zoltan Palffy 👤 Member for 16 years 11 months

no hence the name RESOURCE DEPENDENT. If you want to do this change the activity type to task dependent.

if an activity has been assigned as a resource dependent type of task then the duration will be based on availability for that resource to work on that activity and it will use the RESOURCES CALENDAR NOT the activity calendar.

Try to make the resource calendar as same as the activity calendar and it might do what you want.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts