P6 Nonlabor resource units multiply on import from another datebase
Hi
I've been a member for a long time now & found hints & tips very useful, here's my problem.
P6 Nonlabor resource units multiply on import from another datebase.
I used P6 and had to copy my project to a different computer. I have many resources & costs with in the project activities. however when ever I import a project into a "CLEAN" database, (I stress clean to stipulate that it's not already littered with other resource ID's) my NONLABOR resources, UNIT's only, multiply by a factor of 8.