Proposal EOT still not approved

Dear All,

I have difficulties in the process of having an Extension of Time , my project is an EPC contract project. I want to submit Extension of Time proposal with the reason of delayed work which the work permit is depend on the owner. The case is as follows:

1.       In the contract it is already stated that busbar in the new unit (my project) shall be connected with existing unit 150 Kv substation.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Claim idle resources

Dear All,

Please help in in claim management ,i am totally a fresher to this ,

I want to claim in our next RA BILL claim regarding the idle resources due to stoppage of work in 5 Towers of our Project because client doesnt get statutory clearance & also due to non avalibility of Resouces (AAC BLOCKS) .

What are the main factors to be considered ?& Please guide me to Estimate  this claim

Projet details :30 storey building

Current status:Basement Level

 

 

Thansk & Regards

Sankar Vijayan

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Subcontractor submitts an EOT Claim direct to the Engineer

  1. The overall delay of the project is 95 days (including civil, architectural works, external works and MEP). The client is using FIDIC 1999.
  2. Prior to MEP activities started the project was delayed by 13 days.
  3. The major event occurred when the MEP contractor started chilled water piping 21 days later then the planned date.
  4. The main contractor rejected the EOT claim submitted by the MEP contractor due to various valid reasons.
  5. The EOT claim of the MEP contractor was based on the late approvals of the drawings and material submittals.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Which programs to be used for delay Analysis - baseline or updated

A
Alaa Al haj 👤 Member for 18 years 7 months

Hi To All,

i am preparing Delay Analysis report for Management

one of my friend told me that use original baseline ( without update ) same data date of project start and change the event cause delay by constraints and see the results .

 

while i believe i have to use updated program as of now ( data date as of now )  and compare with baseline  and see the results

 

which one is correct

 

Thanks

ve i have to use updated program as of now ( data date as of now )  and compare with ba

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts