CLAIM ASSESSMENT
Dear Ladies and Gentlemen,
- Read more about CLAIM ASSESSMENT
- 1 comment
- Log in or register to post comments
Got any questions about Claim Assessment
Dear Ladies and Gentlemen,
Hi all,
In a remeasurable contract, can the contractor claim for EOT based on more work required during execution than planned. or a new basline(time) to be fixed accordingly, everytime the planned quantity changes?
For eg:
In the plan, there was 40LM of cable pulling. now during the execution it changed to 100LM and required more time to complete the work (assuming with the same resource as planned in baseline). This delayed the termination of cables, testing & commissioning etc and the contract completion date. can the contractor raise a claim for EOT?
Hi all,
Recently I received a programme, which is scheduled to complete before the contractual completion, say 30 days before, and a buffer activity(30 days) is inserted to meet the contract completion date.
I would like to have your views in case of a delay event in the beginning stage of the project. For eg as follows,
1. Client didn't allot the site to the Contractor as per baseline(say 15 days delay).
All, The contractor submitted an EOT based on impacted as planned method.I evaluated using the same method and found out that Contractor is right for the number of days claimed.Looking on the actual manpower vs. planned manpower, Contractor has only 20 men out of 100 men on the impacted activity. As a consultant, is it possible to reject Contractor's EOT claim because their actual manpower is less than what was planned? Thanks in advance
can someone pls send me a Narrative format on IAP method of claming an extension of time. Needed urgently. Thanks in advance,pls ask for my email if you have one to send to me.
Can anyone tell me of any case law or precedent that states which accepted programme is to be used during the assessment of a compensation event?
If it is retrospective (with agreement to be done retrospectively), should the accepted programme at the time of the CE occuring be used or, should the the accepted programme at the time the CE was notified be used?
Thanks,
Does anyone know about a Forensic Claims Analysis Course online?.
Dear Members,
Background:
Hi,
Can anyone pls guide me on the following as regards EOT claiming:
I am carrying out research on whether a standardised approach to analysing delay in construction contracts is feasible and would appreciate any members that could spare a few moments to complete my survey.