How to display Multiple Critical path in Primavera P6
In Primavera, when we filter critical path, it only show 1 critical path. In complicated project, we might need to show some more “near critical” path.
I will show you how to do it.
Filed Under
In Primavera, when we filter critical path, it only show 1 critical path. In complicated project, we might need to show some more “near critical” path.
I will show you how to do it.
Beyond the Critical Path - the Need for Logic Analysis of Project Schedules
By Thomas Boyle, PE, PSP, PMP
This entry is intended to review the use of the Multiple Float-Path calculation option in Primavera Project Planner (P6) and to offer a brief example of its use compared to BPC Logic Filter.