Planning Engineer, Technip, Cartiere Burgo Paper Machine PM9

START Date
END Date

Project: Cartiere Burgo Paper Machine PM9

Location: Verzuolo (CN), ITALY

Recruited to provide planning, work management, analysis and guidance service for the installation of a lightweight coated paper line, PM9, at Cartiere Burgo Verzuolo paper mill.

Andries Schutte

First Name
Andries
Last Name
Schutte
Professional Since
Oldest experience
Years Experience
25
Guild Accreditation
Awaiting Applicant
Telephone Number
+974 66309956
LinkedIn Profile
https://www.linkedin.com/in/andries-schutte-mrics-bsc-qs-msc-pm-15585923/

PROFESSIONAL

  • Royal Institution of Chartered Surveyors (UK)                                MRICS 1240134
  • Association of South African Quantity Surveyors                             PMAQS 825
  • South African Council for the Quantity Surveying Profession   &

morsi sheta

M
morsi sheta 👤 Member for 21 years 9 months
First Name
morsi
Last Name
sheta
Professional Since
Oldest experience
Years Experience
7
Telephone Number
00201005643951

 

Planner, Technip, Devenick

START Date
END Date

 

  • Work closely with the Project Team to create Level 3 Tender schedules for various projects and clients, in MS Project 2007.
  • Create various option schedules to cover all client options, and compare schedule impact between the options with the project team.
  • Once awarded, convert the project into P3 and include costs, and track progress.
  • Issue monthly S-curves and histograms to the project team, for inclusion into the monthly report to the client.

Project Control Engineer, Technip, Sisi Nubi Field Development– Phase 1, Onshore Facilities for Gendalo Field Development, Sadewa-Z WHP and Pipelines, Onshore Facilities for Gehem Field Development (Indonesia)

START Date
END Date

Established the project setup (project coordination plan, project quality plan, schedule, and budget incl. CTR – Cost, Time & Resources); monitored and rectified the implementation (recovery plan, daily / weekly / monthly report, MOM, supervising document controllers); compiled technical documents, such as Scope of Work and Basis of Design; and handled commercial matters of the project (cost report, change order, level-4 cost estimate, and invoicing)

Estimator, Technip, Kuantan and Segamat Compressor Station Expansion Project (Malaysia), Everest Project - Map Ta Phut (Thailand), Sisi Nubi Field Development Project – Phase 1 (Indonesia), Reformers and Aromatics Complex II Project - Map Ta Phut (Thaila

START Date
END Date

Prepared the bid cost estimate by means of computing the cost of mechanical equipment (pressure vessel, tank, column, heat exchanger, air cooled heat exchanger, compressor, and pump); calculating cost of bulk items; estimating the engineering, construction, and overhead cost; and summarizing all costs in Executive Price Sheet