Planner, Technical Office Engineer, GAMA, QatarGas 3&4 LNG Onshore Project, Ras Laffan, Qatar

G
Gün Göksu 👤 Member for 21 years 2 months
START Date
END Date

Technical Office. Planning (P3), Method Statements & Execution Plans, Proof reading of Client letters & IT, (13 months).

Project details:Ditto above.

●      Company Primavera scheduler, Weekly/monthly reporting of site reports schedule related.

●      Method Statements contact person (type, get approval from client, manage revisions). I have written and approved ~150 MS’ with subjects ranging from excavation works to hydrotesting and equipment installation.

●      Acted as proof reader/translator/typist (focal point) for correspondence with client.

●      Overall IT advisor/troubleshooter for the computer network, ISA/file/data servers.