START Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
1000
How to show the Scheduled % of work for a group of activities.
Cannot show under the WBS Group.
Put all activites under the same WBS and add an activites (WBS summary).
Then it can show the scheduled % for the group of activites.