Tai Wai Station

Planning Manager, New World Construction Limited, Tai Wai Station

L
Li Kwok Sum 👤 Member for 10 years 3 months
START Date
Experience Hours (Planning & Scheduling)
3000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
1000

How to show the Scheduled % of work for a group of activities.

Cannot show under the WBS Group.

Put all activites under the same WBS and add an activites (WBS summary).