Scheduling Manager, Turner Construction, Sacramento Intl Airport Terminal, “The Big Build”

START Date
END Date
Experience Hours (Planning & Scheduling)
50

This ongoing $400 million project with Turner Construction comprises a new 19-gate, 669,000 SF concourse; an automated people mover; a two-level structured roadway; cross-field taxiway and apron paving.  OnTrack’s expert scheduling skills contributed to the time-sensitive conversion of a 1,000-activity P3 schedule into a detailed 2,500-activity, cost-, and resource-loaded P6 schedule, completed in only three months while the project was already in progress.