Ø Identification and Analyzing of Scope of work
Ø Preparation of detailed integrated Level IV Plan
Ø Preparation of work packages for execution of jobs including the detailed method statements
Ø Preparation of manpower deployment and equipment deployment plans
Ø Estimate manpower, spares/material in consultation with Execution and maintenance engineers
Ø Preparation of Weekly Progress Reports to monitor the Pre-Shutdown preparations.
Ø Monitoring of Progress on daily basis and Preparation of Daily Progress Report.
Ø Preparation of Manpower and Equipment Demobilization Plans.