Planning Coordinator , FOSTER WHEELER ENERGY LIMITED, PETRONAS Second Refinery ( PSR- 2 Revamp) Sg. Udang Melaka Malaysia

START Date
END Date
Experience Hours (Planning & Scheduling)
40000
Experience Hours (Cost Management)
500
Experience Hours (Forensic Analysis)
40000

Employer           : FOSTER WHEELER ENERGY LIMITED

Position             : Planning Coordinator

Project Title       : PETRONAS Second Refinery ( PSR- 2 Revamp)

Based                : Sg. Udang Melaka Malaysia

Project Valued   : USD 1.1 Billion

Project Phase Worked: Execute and Operate

Accomplished:

• Established generic format of reporting correctly of progress from 5 piping contractor which approx 1000 km length of various type and size of pipe and equipment modification work

• Established planning phasing of works preparation to shut down and turnaround of existing facility for repair works by system to avoid complete stop of running refinery

• Established correct level 2 & 3 - reporting to stake holder

Complexity:

• Having works to quantify on modification and change of design details to capture into Primavera to show actual progress & deviation from baseline

• Update and re do links ,change sequence of works on task activities on project schedule to be align what actual performed on site and establish the correct critical path activities .

• Managing contractors work progress on mitigation slippage and re-phasing of works on site