Planning Engineer, Leighton Contractors (Asia) Limited, Gold Processing Plant Project

J
Joseph Ador 👤 Member for 15 years 9 months
START Date
END Date

An EPC Contract of Accommodation Buildings (23 no.) and Gold Processing Plant. Gold Processing Plant comprising of 8 Leach Tanks 18m in diameter, Primary Crusher complete with mechanical and controls equipment, Structural Conveyors, Tailings Pond, Surge Bin, 2 Ball Mills, 1 Sag Mill and Gold room.



 Establish Detailed Contract, Working and Look Ahead Programmes.

 Prepare Progress Report S-Curve/Histogram/Gant Chart and developing Weekly, Monthly Progress Report, Recovery Plan and Look Ahead Programs.

 Provide Materials Take-off (MTO).

 Coordinate with Senior Planner and Site Managers in making working schedule.

 Directly reporting to Structural and Mechanical Superintendent, giving detailed information and progress report of the actual received and outstanding structural items on site. Provides site inspection and supervision.

 Establishing Civil, Structural, Mechanical, Piping and Electrical Progress Monitoring Update.

 Directly reporting to the Project Manager and discuss project status issues.

 Attend/hold Weekly Progress meeting. Give assessment/analysis on the previous production and target production.