Equestrian facility comprising race course, hospital, riding school, staff accommodations, etc. spreading over 1.5 sqkm with the project cost USD 450million. Leighton was the main contractor for the Design & Build contract. Key responsibilities on the project are below
- · Monitoring and weekly reporting of contract program
- · Review of subcontractors programmes
- · Implementation and monitoring of control tools
- · Assisting package managers by writing detailed programmes relevant to the package
- · Attending progress review meeting
- · Coordination with site supervisors and assisting them with short range programmes