Search

Progress - Summary Progress

Forum Topic

Is it possible to proclude the progress line from including summary lines? i.e showing an average of the progress of activities within this as this information isn't as important. I am more experienced in using Asta Powerproject, is it normal for the...

Dec 11, 2018

Resource Filter

Forum Topic

Hi all, Is anyone able to advise me on how createa a filter for a resource in the normal activities view please? The end result that I'd like is to be able to give each resource a pdf bar chart of their programme of works. I'm using Primavera P6 v17....

Dec 11, 2018

Restore P6 Pro Standalone (SQLite)

Forum Topic

Dear Members,I've P-6 file name as "PPMDBSQLite". This is only file as primavera database of all my projects. I want to access them on another PC. Could I access them? What should be the way to upload?I'm worried about this because this is only backu...

Dec 12, 2018

Understanding the Planned Dates in Oracle Primavera P6

Blog

By Yaser A. Al-Bustanji CPCM, ACIArb, PMP, PMI-SP, PMI-RMP, November, 2017IntroductionOf the many different types of date fields in Oracle® P6™, the most controversial and misleading dates are, "Planned Start" and "Planned Finish" dates of the activi...

Nov 17, 2017

The general thumb rule of Fabrication Productivity

Forum Topic

Dear Sir, I am new in planning section . I am now preparing a planning sheet regarding fabrication work. kindly guide me how much productivity and manpower will consider in verious section fabrication.like 1. shop floor heavy fabrication .2 . on site...

Nov 19, 2017

Different duration for same Project.

Forum Topic

Hi everybody ,I am a new user of Primavera.I am facing an issue regarding total duration of a project which is showing two different duration in two systems. I have imported this project to the second system from the first One where it was created.I ...

Nov 20, 2017

Microsoft Project and Super Critical Bars

Forum Topic

Here's how to create Gantt chart bar in Microsoft Project to highlight activities that are already behind or super critical http://ed.gr/h3l3

Nov 20, 2017

change order and reflection in baseline

Forum Topic

All change order modify the baseline in some way, such as cost, scope or time. but we do not create a new baseline everytime.how do we reflect this change order which only modifies part of the basline, in the baseline?for example, lets say we are bui...

Nov 21, 2017

WBS Import from Excel

Forum Topic

I have created some development code that allows me to Import a WBS Structure from an Excel file into an XER File directly & have been testing this with my own projects, along with some made up examples to try & test it out properly.I am looking to f...

Nov 22, 2017

Guild Corporate Members

Page

GUILD OF PROJECT CONTROLS (GPC) CORPORATE MEMBERSThis is our effort to help YOU the employers of our community and it is about being able to:Better understand your ENTIRE Project Controls environment in terms of workforceAssess the competence of all ...

Nov 22, 2017

P6(R8.4) get freeze when trying to export

Forum Topic

Dear Valued member,I have got a serious issue when exporting P6. I am using barnd new Toshiba Tecra Z50-C laptop. And I am using P6 as standalone.Whenever I am trying to export file , my laptop get freeze. In my current employer no body use P6 and th...

Nov 23, 2017

Display Options

Forum Topic

Hi All, I need some assistance in regards to displaying a two weekly programme. Firstly, I have all non-working time showing but with a grey fill, how can this be made to go behind the subheadings?Secondy, is there a way to specify a time period to b...

Nov 23, 2017