predecessor or successor
Forum Topichi, is it important to have predecessor or successor in all the activities.In my planning file, some doesnt have Predecessor.will it creat any problem to my plan in later stages? Plz help me
hi, is it important to have predecessor or successor in all the activities.In my planning file, some doesnt have Predecessor.will it creat any problem to my plan in later stages? Plz help me
Dear All,I would like to open an whatsup group on Forensic Claim analysis. if interested , email your mobile no to [email protected], Haresh Jayanth
Here the Primavera P6 Professional Network Diagram's capabilities are explored http://ow.ly/YSkKG
Hi Guysi want to know about unit % Complete.in my programm Activities window shows 1.68% whereas Resourece assignment shows 2.23%.whats wrong in my programm?i attached following pics.can you explain me details.Pic-01Pic-02
Hi Planners and Project Managers,Could any one tell me the outline (main sections) of quality manual?Best,Moutaz
Hello -I'm trying to put a newer schedule's activity statuses into an older schedule (physical % complete, actual start, actual finish, and remaining duration).Is there a way to somehow copy this information from one schedule to another? (versus manu...
Can anyone out there explain why P6 doesnt alway calculate actuals?When we update Units % complete for an activity, P6 calculates its Actual Units (as earned) for the first time but it stops updating Actual Units for any further Units % updates. Rath...
Do you manage resources that you don't own? Leading teams across competing company groups puts the project manager in a fragile situation. Read more http://ow.ly/YYy1U
i everyone, here i would like to request if anyone could share me some of best practices of Ship Building Schedule. Its for training purposes and i just want to share to my class since they are new and from Shipyard Company. You can reach me via emai...
Hello all, I am new to this forum.I would like to create in the table of my Gantt Chart an indicator showing if one or more resource is assigned to the task (ie green light if any resource, red if none).i am trying to use a custom field indicator but...
Dear All,I am working with MS Project 2010. My calender is 24hr working 7 days a week.I need to show a column which highlights the planned % complete for a given status date.This is so we can present to our client (for example) - we should be 40% co...
Hai to all, please help me anybody, how to create a piping project having scope (200000 IM and 19000 ID) IN PRIMAVERA P6. MANI
Invoice software for all the business is essential tool. How to create a invoicing software? Which software is best for invoicing?
Hello! I’m a student from Latvia and currently I’m writing my master thesis about „Perception in different cultures of successful project”. For a quantitative analysis I have arranged a survey covering questions about project management. I woud lov...
There shouldn’t be tension between the program and project managers and the PMO team: whether you all report to the same director higher up the hierarchy or not, you are all part of the same extended team. Here are 5 ways to bring the PMO closer to t...
Dear Planners,I want to rename 1000 activities using Global change. Can you help me....
Hi All,If anyone is interested in watching Dr. Steve Squyres presentation on the Mars Rovers project, you can check it out free for a limited time: http://www.mpug.com/mars-rovers-the-ultimate-project/Enjoy!
Hi all,I'm asking for professional advices that need your kindly help. Short backgrounf of myself -I have been working in Planning (in tender team, construction industry) for 2 years. Before I was working in a geotechnical engineering field as I have...