unit % Complete ( attachments )

Hi Guys

i want to know about unit % Complete.in my programm Activities window shows 1.68% whereas Resourece assignment  shows 2.23%.whats wrong in my programm?

i attached following pics.

can you explain me details.

Pic-01

Image removed.

Pic-02

Image removed.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

run a global change make sure that 

where activity status is not equal to comeplete 

then duraiton % complete = physcial % ciomplete 

A
AEJAZ AHMED AHMED 👤 Member for 12 years 2 months

A-1 type task dependent

A-2 Fixed Duration & Units

A-3 Physical % complete

A-4 & A-5 i used default setting.

[[wysiwyg_imageupload:3621:]][[wysiwyg_imageupload:3622:]]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Hard to tell can not see the pics

1. Is the activity type task dependent or resource dependent ?

2. What are you using for duration type ? 

3. What are you using for % Complete type ?

4. Under Calcluations do you have Link Actual and actual this period units and costs checked

5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts