PMO organization Chart within an organization
Forum TopicHi All,Can anyone illustrate the PMO organization within an organization, where is the PMO be placed?Regards,Muataz
Hi All,Can anyone illustrate the PMO organization within an organization, where is the PMO be placed?Regards,Muataz
Watch the following video to learn how quick and easy it is to install Primavera P6 professional is a standalone application using the SQLite database. This video depicts the software being installed on a Windows 10 operating system http://ow.ly/MfGq...
Hi Planners,A baseline schedule showing that the start date of the project "milestone task" is not critical "9 days float", some of the succesor tasks has a constraint "start no earlier than". I changed the constraint of those successors to "Must sta...
Hi everyone,I plan to take the PMI-SP exam in the near future and i have a few questions.Did anyone else here took the test recently? How much time did you dedicated to studying?What other materials did you used besides PMBOK and the Practice Standar...
Dear friends, I found very pecular problem. I am using P6v7, in my baseline schduele (resouce loaded, fixed budget) Planned value is showing as 122,757,666 for the DD is 22.apr.2017 but for the same date if you see cum.BL project total cost in Activi...
Hi all,There is any way in p6, to calculate EV based on EAC rather than BAC? Thanks
Hi Planners,I have a baseline schedule and I am filling the resources in the resource sheet but I faced an obstacles that I have human resources "Project Manager" that is working on the project since starting until closing out with a fixed salary, ho...
I am aware there is ample information out there to create an S Curve via P6 without entering total manpower for each task (I do not know how to currently do this, but will do the research to save people from having to post informaiton that is already...
I have rebaselined a project, but for the tasks in progress, the Cum BL Project units are different from Cum Actual Units. Why is this? Have I got a setting set incorrect, or can I not rebasline when I have tasks which are in progress? Thanks in adv...
Project planning and scheduling processes follow a management framework called the Project Implementation Model (PIM). Such model divides the project into sub-boundaries called stages, gates, or checkpoints.Does not really matter what proprietary ter...
Hello Everyone,I'v created baseling schedule contains over 7000 activities. I have to update them now by activity % complete. Is there and fast way to update them by excel if I have the data already in excel?
Here's a look at Microsoft Project and schedule milestones http://ow.ly/GNXF30bPwuH
Has anyone ever created a standard S curve in which you could then insert a project duration and total budget to predict future cash flow?I am looking for something very rudimentary, with full understanding that there will be great variance between t...
20-May-2017 My first book signing event went well today at Indigo Signal Hill. I met a lot of interesting, intelligent people and was able to introduce the book to them. Had some lively discussion with a few who said that the book was timely. Some pr...
Dear All,This is Umashankar Presenting greetings of the season!I am currently involved in producing a revised schedule. The Project has a contract duration of 3 years; of which 1 1/2 years is already elapsed. The client issued a Variation Order for...
Hello. I'm doing a study on the classification of Project Management software in a university thesis.With this goal, I want to ask you if you could kindly fill in this short questionnaire asking to evaluate (with a score) the features that a Project ...
Hi everyone, I'm new here and need help in preparing time chainage diagram as this is new to me and I don't have any idea how to complete this. I need to prepare and complete the project by 26th and any kind of help will be highly appreciated. Thanks...
Hi all. Im conducting some research and hoping there may be some project co ordinators involved in capital works type projects willing to have a 20min phone chat/interview with me? Im not involved in the industry and trying to gather an understanding...
Quick Tip: Here's a look at the Primavera P6 Professional automatic schedule update http://ow.ly/Rzor30bVZhk