I have rebaselined a project, but for the tasks in progress, the Cum BL Project units are different from Cum Actual Units. Why is this? Have I got a setting set incorrect, or can I not rebasline when I have tasks which are in progress?
Thanks in advance
[[wysiwyg_imageupload:4805:]]
actual unist are based on progress the budget units are static. They will always be different