Search

Please explain earned and actual hours

Forum Topic

Hi, I'm new withing planning, and I can't seem to figure out what the differences between planning qty, earned qty and actual qty is. Example:Current Budget for welding is 20 760 hoursPlan Qty = 1 810Earn Qty = 504Exp Qty = 1696 And planned man power...

Nov 30, 2023

Which P6 version/release do you use now?

Forum Topic

Is anyone updating Primavera to the latest release?Organisations I am working with typically use a 3-5-year-old Primavera version.   Even when an upgrade is considered usually organisations don't feel comfortable upgrade P6 to the latest release. Is ...

Nov 30, 2023

should likely error in APPROVED baseline be allowed to stand?

Forum Topic

should likely error in APPROVED baseline be allowed to stand?  In a sequence of work on the critical path is a 5 day "sub-contractor mobilization" activity.  Seems like an obvious error - they could likely mob anytime - such as - as the predecessor w...

Nov 30, 2023

Critical activities with Negative float

Forum Topic

Hi everyone, I know that it is not best practice to have a mandatory finish constraint and negative float on your programme, but contractually we have to have those two in our programmes. Now the question is P6 shows all the negative activities as cr...

Dec 3, 2023

How WPM Works

Forum Topic

Work Performance Management (WPM) is a methodology developed by Mosaic Project Services Pty Ltd to offer a simple, robust solution to the challenges of providing rigorous project controls information on projects that cannot (or are not) using CPM and...

Dec 5, 2023

what if the baseline is found to be wrong?

Forum Topic

what if the baseline is found to be wrong?  -  can you then claim that the project is behind or ahead when the baseline critical path has changed?

Dec 5, 2023

Global and Project calendars

Forum Topic

Hi AllHow do you tell whether an assigned calendar on P6 is the global or the project calendar if you have the same calendar name under the global and the project calendar libraries?

Dec 6, 2023

Leveling issues, "pinning activities in place"

Forum Topic

Hello, For a while, I have been facing some issues with leveling resources on P6. I understand the principle upon which it calculates start dates, but I'm facing issues "pinning" some activities down and forcing start and finish dates. For example I ...

Dec 11, 2023

Productivity Calculation for Steel Works

Forum Topic

Hi all.I need help on the productivity calculation for structural steel worksHow many manpower we should consider for how many tonnage.Now i have 700ton steel beams and column. It is for the construction of 6 floor factory expansion. The duration is ...

Dec 12, 2023

Productivity Calculation for Steel Works

Forum Topic

Hi all.I need help on the productivity calculation for structural steel worksHow many manpower we should consider for how many tonnage.Now i have 700ton steel beams and column. It is for the construction of 6 floor factory expansion. The duration is ...

Dec 12, 2023

DCMA 14 and Level 2 schedule

Forum Topic

Needing a reference or guidance. A L2 schedule should be a roll up from a L3 schedule. Sometimes however a L2 schedule may be an early deliverable long before a L3 is developed fully due to lack of design and/or subcontractor information. Maybe L2 is...

Dec 13, 2023

LLM and Project Management - The Intelligence in AI is limited!

Forum Topic

The best known LMM (Large Language Model) is ChatGPT. The developers acknowledge ChatGPT sometimes writes plausible-sounding but incorrect or nonsensical answers. Fixing this issue is challenging, as during the LLM training there is no single source ...

Dec 20, 2023

Critical Path Characteristics and Definitions

Forum Topic

[[wysiwyg_imageupload:8564:]]I’m wondering what is causing the confusion appearing in so many posts lately concerning the definition of the critical path. Is it:A lack of knowledge?People being out of date and using superseded definitions?People not ...

Dec 29, 2023