Please explain earned and actual hours

Hi,

 

I'm new withing planning, and I can't seem to figure out what the differences between planning qty, earned qty and actual qty is.

 

Example:

Current Budget for welding is 20 760 hours

Plan Qty = 1 810

Earn Qty = 504

Exp Qty = 1696

 

And planned man power is 48, while actual man power was 45.

Can someone please explain to me or give an example of what planned, earned and exp qty is? And what the differences are?

J
Joselito Santillan 👤 Member for 17 years 10 months

Planned Qty = 1,810

Planned MP = 48

Actual MP = 45

Exp Qty = 1696

If 48 (planned) can do 1,810 (planned), 45 (actual) is expected to earn 1696. But you only achieved 504 (actual/earned value). What factor/s have affected your productivity?

Profile picture for Patrick Weaver
Patrick Weaver 👤 Member for 25 years 4 months

These consepts are derived from Earned Value Management:

Planned quantity = the amount of the budgeted work planned to be completed in a period, or to date.

Earned quantity = the amount of the budgeted work actually achieved in a period or to date (measured using the same basis as the budget). In your example ony 28% of the planned work was achieved.

Actual quantity = the number of welding hours actually booked against the job in the same period or to date..... This activity is a total mess!!  

For more on this and some free resources see: https://mosaicprojects.com.au/PMKI-SCH-040.php#Overview 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts