Critical activities with Negative float

Hi everyone, I know that it is not best practice to have a mandatory finish constraint and negative float on your programme, but contractually we have to have those two in our programmes. Now the question is P6 shows all the negative activities as critical and also makes them RED on the Gantt chart. Is there any automatic way that it shows the highest negative number as the critical ones only?

I made a screen shot of one of the projects for better clarification. As you can see, planned completion has -341 days float and makes it Critical, but also activities under documentation and handover are also critical, although the float is -338.

 

 

screenshot_2023-12-04_075301.png

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts