Search

Asta PowerProject Password protection

Forum Topic

Somehow my PowerProject file has a password set.I DO know the password but I don't want to have one on it. How do I remove the password?I can't see any option on any of the task ribbons and nothing in the file properties dialogue...?

Jan 20, 2021

Project Managers' challenges with project planning.

Forum Topic

I am curious what the biggest problems are that Project Managers face with regards to project planning. Would you give me some insight by answering a quick 3 question survey? https://forms.gle/iQDhFitBu9WBzMyK9

Jan 21, 2021

Resources not showing on histogram

Forum Topic

Hi I've added resources to my level of effort bars (made more sense i thought, as you would have 1 gang complete x amount of activities), yet when I come to look at the histogram they don't appear? I never needed to do resource loading before, and th...

Jan 21, 2021

Report running issue

Forum Topic

Hi all,probably more aimed at P6 administrators...I've been using P6 for monthly reporting for a long time now. Simple process of opening all relevant plans, then runnning a saved reort to output remaining early units by Activity ID. This month, all ...

Jan 25, 2021

Global Activity Codes Export

Forum Topic

Global Activity Codes are not getting exported in the xer file. I tried opening the exported xer files with Wordpad & also in another PC but the global activity codes are not present in both cases. How to export Global Activity Codes in the complete ...

Jan 27, 2021

Storage not found

Forum Topic

Today I received a schedule file that had a couple of references to a storage not found.I found the first reference was in the previous version used for comparison, a not so obvious issue. I set resource leveling option to previous version and erased...

Jan 28, 2021

Material is spent on …

Forum Topic

Material is spent on …Please look at the following scenario, total remaining supply is greater than total remaining consumption but it is impossible.  Dialog says material is spent on 04-02-21 but I believe it is a bit latter due to consumption on ac...

Jan 29, 2021

Free Webinars in February 2021

Forum Topic

Here is a list of free project planning & scheduling webinars that will take place in Februaryhttps://www.plannersplace.com/blog/free-webinars-feb-21

Jan 30, 2021

Duration calculation when using 2 different Calendars in MS Project

Forum Topic

Hi,I'm hoping somone can help me with the following problem I'm having with MS Project. I have a project with Construction Activities (Standard Calendar appropriate) and Shutdown Activities (operating over 24hrs, 7 days a week calendar).I can create ...

Feb 1, 2019

Forecast Manhours Calculation - Engineering Deliverable

Forum Topic

Hello Everyone, Can anyone explain how to calcualte the Forecast MAnhours for a Engineering Document/Delvierables. Say for Example DeliverableBudgeted ManhoursPlanned %Actual %Earned ManhoursActual ManhoursForecasted Manhours ABCDEFTank Foundation Dr...

Feb 5, 2019

P6 Tracking Progress

Forum Topic

HiI have started with P6 few months ago.My issue is:Tracking progress on status tab: task Fixed Duration and Units, % complete type Physical. I chek the started, then Remaining days and % Physical based on actual and remaining days. If the task is de...

Feb 5, 2019

EOT

Forum Topic

Hi there.We submitted a baseline at the start of the project that was approved and had been following the same for some time. Then we revised the baseline by changing the construction methodology to change the sequence of activities and also the dura...

Feb 6, 2019

Text will not wrap after Import from Excel

Forum Topic

Hello all,I have successfully imported data to P6 via XL. I have some rather long "Activity Names" that refuse to wrap inside the field.I have tried ALL "Table Row & Font" settings to no avail.IF I copy the text into MS Word, then paste it back into ...

Feb 6, 2019

Change date format on Group & Sort

Forum Topic

Hi all,Trying to Group & Sort by Start Date (Group Internal =Day) and can't seem to find a way to change the date format. In my User Preferences, I have the Date Format set as Day, Month, Year yet in the Group & Sort it shows as Month, Day (US format...

Feb 10, 2019

Download Primavera PPM ver 18 from Oracle website

Forum Topic

Hi,I was trying to download the Primavera PPM stand alone ver 18.8, from oracle website.No I am stuck at the window, asking for the connection string and the data base configuration with username and password.Have anyone experienced it while download...

Feb 10, 2019

How can I Schedule from a known finish date backwards....

Forum Topic

I saw a scheduler do this once in P6 and I trying to replicate what he did. Say I need to be Finished on 12/31/19 and I have a schedule built out.  How can I schedule from that date backwards essentially given me the latest start of all activities to...

Feb 11, 2019

Man hours in oil and gas industry

Forum Topic

I always use a manhours in my job (oil and gas) with budget in manhours and lot of things in relation with it,but i always ask in my mind a question,why we use Manhour unit in the planning ?

Feb 11, 2019

LoE budgeted units not matching activity calendar

Forum Topic

I have a role assigned to a LoE (fixed duration & units/time) which has a standard 5 day calandar.Budgeted units / time is 100% and the total budgeted units in the resource assignments window match the activity duration. Planned dates match forecaste...

Feb 13, 2019