LoE budgeted units not matching activity calendar

D
Dan Pitts 👤 Member for 14 years 6 months

I have a role assigned to a LoE (fixed duration & units/time) which has a standard 5 day calandar.

Budgeted units / time is 100% and the total budgeted units in the resource assignments window match the activity duration. Planned dates match forecasted.

 

The issue is that in the resource assignments spreadsheet it is showing 25 units in June 2019 where the calendar only has 20 working days. Why are the budgeted units not aligned to the activities calendar?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

if you assign a budget to a LOE activity type you MUST assign a resource CURE or the units will all stuck up on the data date.

D
Dan Pitts 👤 Member for 14 years 6 months

Hmm... have just restarted Primavera and all appears to be displaying as expected in the resource spreadsheet. Weird!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts