Hi
I've added resources to my level of effort bars (made more sense i thought, as you would have 1 gang complete x amount of activities), yet when I come to look at the histogram they don't appear?
I never needed to do resource loading before, and this project is for studying.
Kind Regards
Philip
of you use a a LOE type of activity then you MUST assign a resouce curve to that LOW activity or all of the resources wil stack up on the data date.
fro the LOE activity click onthe resource tab at the bottm
then rigth click and select customize resource columns
expand the general category and select curve
then click in the curve box and select a curve teh standard curve is Linear
done