Search

Activity Delay in p6

Forum Topic

Hi every onecan  Actrivitiy Has a delay in days more than the Updating interval ex.: if th update Int.=30daysafter update can the activity has more than 30 days delay greater than the previous delay ???

Sep 22, 2016

Tracing Activity in HUGE Project

Forum Topic

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cum...

Sep 22, 2016

Tracing Activity in HUGE Project

Forum Topic

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cum...

Sep 22, 2016

5 Annual Objectives for PMO Leaders

Forum Topic

You might be wondering why we’re focusing on annual objectives right now, when typically you’ll see articles about goal setting at the start of the year. It’s because now is a great time to be reflecting on objectives and making sure that you and the...

Sep 23, 2016

Resource Distribution Doesn't Work Correctl, Any Idea?

Forum Topic

Hello,I was trying to check an activity's resource distribution from Resource Assignments tab but eventually I realised that eventhough I increased the remaining time of that activity, the distribution of resource doesn't change. It only shows exact ...

Sep 24, 2016

CAREER ADVICE

Forum Topic

HELLO EVERYONE, I have recently comleted B.TECH IN INSTRUMENTATION ENGINEERING in India. Would it be wise to start off  my career as Planning engineer?? Do planning engineers in instrumentation field have good scope for career advancement?

Sep 24, 2016

Increased Manhours when Importing from MSP to P6

Forum Topic

When I import a plan from MSP to P6, the work shown in budgeted labour units increases by approximately 1500hrs. I've tried changing the importing settings as well as the calculation settings on the project but it doesn't seem to make any difference....

Sep 27, 2016

Airport Construction schedule

Forum Topic

Hi All,  who can share with us basic things to consider we you plan for Airport construction and if possible share typical schedule shows major activities  thanks 

Sep 28, 2016

Formula Help - Omit summary tasks from formula?

Forum Topic

Hello, The below formula will give a red cross at a task which have an actual%complete less than the planned%complete, and a tick in other cases. switch(PlannedPercentComplete(CB,na)>PercentComplete,high,PlannedPercentComplete(CB,na)<=PercentComplete...

Sep 28, 2016

Baseline Resources - reports

Forum Topic

Good afternoon all, I've been asked if I can generate a report from P6 to show our current plan resource amount vs our baseline resource amount. i.e. when we baselined a job we had for example 20 tons of steel used, as the project has progressed this...

Sep 28, 2016

Baseline Resources - reports

Forum Topic

Good afternoon all, I've been asked if I can generate a report from P6 to show our current plan resource amount vs our baseline resource amount. i.e. when we baselined a job we had for example 20 tons of steel used, as the project has progressed this...

Sep 28, 2016

Total Budget

Forum Topic

Hi everyone,I'm trying to make a simple report showing the budget for each WBS.Is there any way to show a total for everything?

Sep 29, 2016

Baseline Critical Path

Forum Topic

Hi MSapiens/Planners,I'm working on an MS Project file for quite sometime. It has got a baseline that was made long ago. Now, i want to see the critical path in that baseline. Can someone suggest me on sorting this out, using either custom filters or...

Sep 29, 2016

How long would it take to complete PMP certification?

Forum Topic

Now, I have searched a lot of communities and have read a lot of blogposts about the time it would take to complete my PMP certification, but they all quite vary from each other. So, I would like to know if anyone of you has completed PMP certificati...

Sep 29, 2016

Introduction

Forum Topic

Hello Everyone,   I am new here in this forum.

Sep 30, 2016

Error when updating Remaining Units / Time

Forum Topic

Hello, I'm trying to update the Remaining Units/Time in the Resource Activities in my schedule. I have done an export, update the file and when I import I get the following message:Error: Cannot assign the same Resource: RSRC: xxx to TASK ActivityID:...

Sep 30, 2016

how to calculate the peak consuption of concrete with ms project

Forum Topic

Dear All,I'm going to create a matirial resource concrete with standar rate  1/hr and assign for each concrete activities in the gant chart the  concrete resourse then in ihe unit I assign the quantity in cubic meter.  Afetr filter for concrete and s...

Sep 30, 2016