Baseline Resources - reports

Good afternoon all, 

I've been asked if I can generate a report from P6 to show our current plan resource amount vs our baseline resource amount.

 

i.e. when we baselined a job we had for example 20 tons of steel used, as the project has progressed this has changed a few times and I want to be able to get out of the P6 baseline what our original figure was so we can see how far it has changed in the time between. 

I'm fairly sure that without detaching the baseline and going into it manually the above report can be done.  My line manager is convinced P6 allows this.  

Can someone give us a defintive answer?  if I'm wrong then great can you tell me how to do this, if I'm right and it needs detaching then someone else has some work to do :)

 

thanks

 

Thom

D
David Kelly 👤 Member for 21 years 7 months

Zoltan's reply is correct if you simply want to know if the cost has grown overall.

If you want to know which activities are responsible for the growth, pivoting the data into a time (rather than activity) based report will still leave a lot of work to do....

Z
Zoltan Palffy 👤 Member for 16 years 10 months

view show on bottom activity resource usage

on the right hand silde click Activity Usage Profile options

now under data select units 

now under filter for bars/curves select material

now under show bars/curves select Baseline and either Budgeted, Actual  or Remianing or ALL of them

you can also add a culumative cirve is you want by checking Cumulative

Then select Apply  

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts