Good afternoon all,
I've been asked if I can generate a report from P6 to show our current plan resource amount vs our baseline resource amount.
i.e. when we baselined a job we had for example 20 tons of steel used, as the project has progressed this has changed a few times and I want to be able to get out of the P6 baseline what our original figure was so we can see how far it has changed in the time between.
I'm fairly sure that without detaching the baseline and going into it manually the above report can be done. My line manager is convinced P6 allows this.
Can someone give us a defintive answer? if I'm wrong then great can you tell me how to do this, if I'm right and it needs detaching then someone else has some work to do :)
thanks
Thom
Zoltan's reply is correct if you simply want to know if the cost has grown overall.
If you want to know which activities are responsible for the growth, pivoting the data into a time (rather than activity) based report will still leave a lot of work to do....
view show on bottom activity resource usage
on the right hand silde click Activity Usage Profile options
now under data select units
now under filter for bars/curves select material
now under show bars/curves select Baseline and either Budgeted, Actual or Remianing or ALL of them
you can also add a culumative cirve is you want by checking Cumulative
Then select Apply