Search

How to turn off annual weekly numbers

Forum Topic

I am trying to add week numbers to the top of the programme in the date zone. I can do this this after week 52 it goes back to week 1, but I would like the week numbers to carry on as the project I am working on is over 2 years and would like the wee...

Aug 30, 2013

SDK and Calendars

Forum Topic

I am trying to find detailed calendar information using the sdk i.e is date x a working day. In the main p6 database the calendar table has a field clndr_data which contains days off, days of week etc but this doesn't seem to be available in the Cale...

Aug 31, 2013

P6 scheduling help

Forum Topic

hello - hope someone can help - I am new to primavera planning with P6 and there is something i dont understand and would love some help- P6 set up : fixed duration units/time - physical % - no resource assigned to any activityscenario :I have 3 acti...

Sep 1, 2013

How to set budgeted earn value unit cut off

Forum Topic

Hi,i have a difficulty on how to get budgeted labor unit as per my cut off time. Previously i always use 'Update Progress' and then i put there date and my cut off time. Example, 2-Sept @ 1600hrs. Then i open column for 'Earn Value Labor Unit'. Expan...

Sep 2, 2013

How to plan a schedule?!-Please help

Forum Topic

Hi all,I have recently been made aware that the schedule should have most of the activities with FS links to make out a sensible (delay) analysis.I have tried to prepare a schedule in line with the above philosophy.I have observed the following point...

Sep 2, 2013

Approval of Baseline Schedule

Forum Topic

Recently, we received comments by the Client's Representative on the submitted 'Baseline Schedule'. One of the comment is to incorporate quantities in Primavera P6 and to provide the same along with production rates in 'Excel' format also.My question...

Sep 3, 2013

Management of Schedule Updates for Multiple Projects

Forum Topic

I'd like to hear how other Schedule Managers or Project Controls Manager handle getting timely schedule updates from those responsible in performing the updates.  Currently I'm charged with maintaining a portfolio of 15 projects.  There are 13 Projec...

Sep 3, 2013

Activity necking

Forum Topic

Hey All! I was wondering if someone can help me. I am trying to neck an activity that is critical. the calendar attached to the activity already has the non work period into consideration. When i go to the bar setting and checked the calendar non wor...

Sep 4, 2013

Histogram Problems when trying to show works done on the weekends?

Forum Topic

I am trying to show a histogram at the bottom of the bar chart, to show the amount of concrete that we will be pouring on site each day.  However the bar chart calendar is a mixture of 5 day, 6 day and 7 day working.  The histogram does not show the ...

Sep 4, 2013

Material Allocation on Histogram Problems

Forum Topic

Hi All,I am allocating material quantities to certain activities on the bar chart in order to produce a histogram.  I am putting the total material quantity total in the correct column, however in the histogram it is picking up the total quantity in ...

Sep 4, 2013

Define correct relationship between activities

Forum Topic

Dear Friends,For a long duration of Project , we should perfom some activities which can start at data date but compeletion of these activies at the start of Projct is useless let me give an example;Around 3 years later we should paint the building a...

Sep 4, 2013

Interview Question for the Planning Engineer

Forum Topic

Hi guys, Given below are list of interview questions faced by Planning Engineer , other than their personal and Experience. if anyone like to add more u are welcome pls .............I would appericiate if some has brief answer of the questions listed...

Sep 4, 2013

Custom field to show only PM name

Forum Topic

Hi there, I am using MSP 2010 prof. I have a file with over 90 projects. In the Gantt view I want to create a custom field named PM that only shows the assigned PM and not all the other assigned resources. Not all projects have a PM assigned. Any ide...

Sep 5, 2013

Activity Relationship - Predicament

Forum Topic

 Hi all,I have recently been made aware that the schedule should have most of the activities with FS links to make out a sensible (delay) analysis.So, I have tried to prepare a schedule in line with the above philosophy.I have observed the following ...

Sep 5, 2013

Project Management in Emergency Response Projects

Forum Topic

CRC Press’s Handbook of Emergency Response: A Human Factors and Systems Engineering Approach was released last week. Edited by Adedeji Badiru and Major Leeann Racz, both of the faculty of the US Air Force Institute of Technology, it is a most interes...

Sep 5, 2013

Is Primavera R8.3 a stable release like R8.1 & 8.2?

Forum Topic

Hi, Please share your experience and thoughts about the Primavera R8.3 release. Is R8.3 a stable release like R8.1 or 8.2?. Is there any major technology or UI changes or  mainly talking about additional capabilities within the same framework as R8.2...

Sep 6, 2013

updating of tasks

Forum Topic

Hi people Hope you can help, something that has just started happening in my version of P6 ver 7I create a schedule, with logic links in etc when I hit F9 to schedlue all the tasks come backto start on the data date therefore destroying the schedule ...

Sep 7, 2013

Tracking the projects

Forum Topic

I hope every one will be fine. I need some help form u guys , I am planning engineer in a plant services department which deals with oil and gas , petrochemical plant turnarounds. We do turnarounds which merely have 15 to 20 days. My organization is ...

Sep 7, 2013