I am trying to add week numbers to the top of the programme in the date zone. I can do this this after week 52 it goes back to week 1, but I would like the week numbers to carry on as the project I am working on is over 2 years and would like the week numbers to continue.
Does anyone have any ideas how to do this, as I know it can be done, but just cant find the right option?
Thanks
That was exactly what I was looking for. I had Fiscal Units instead of Elapsed Units selected in the first column?
Thanks for the quick reply
Nathan,
Right click on the date zone and select properties from the menu that opens up to open the 'Date Zone Properties' dialogue, you then need to look to the right-hand side of the 'General' tab. In the box you need to select
Type: Elapsed Units
Time Unit: Elapsed Weeks
Quantity: 1
By the sound of things you have selected 'Annual Units' instead of 'Elapased Units' in the first column. Hope that helps!